Intersection improvements information
This is an engagement opportunity for the Lithia Pinecrest Road at County Road 39 Intersection Improvements project. This engagement is to inform the community of upcoming intersection improvements. The feedback period for this project will be open from May 12 to May 26, 2026.
Quick Facts
- CIP#: 69695000
- Location: Lithia
- Project Type: Intersections
- Phase: Planning
Schedule
- Planning complete: Mid-2026
- Design complete: Mid-2030
- Construction begins: Early 2031
- Construction complete: Early 2033
Budget
- Total: $10,900,000
- Planning: $353,146.58
- Design and Land: $3,325,799
- Construction: $7,221,054
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change.
Overview
- Provide dual left-turn lanes on both Lithia Pinecrest Road approaches and single left-turn lanes on both CR 39 approaches. Provide single right-turn lanes on all approaches.
Update signals, signing and pavement markings to include pedestrian and bicycle accommodations. Upgrade drainage and add stormwater management ponds to accommodate additional pavement for turn lanes, sidewalk, shared use paths and curb and gutter.
Objectives
To improve traffic flow, safety, and multimodal access at the intersection by adding dedicated turn lanes, upgrading traffic control devices, enhancing pedestrian features, and improving drainage infrastructure to support the expanded roadway and related improvements.
Questions and Feedback
For more information about this project please contact (813) 635-5400 or visit At Your Service