Projects Planned at Miller Rd. and Dover/Little Rd.

Durant at Miller Rd. intersection improvements

Overview and objectives

  • To improve transportation, mobility, and access for vehicles and pedestrians including retrofitting to comply with the Americans with Disabilities Act (ADA), the four-way stop intersection will be converted to a roundabout with turning movement improvements and pedestrian enhancements. Sidewalks will be updated to improve pedestrian safety, specifically ADA ramps, curbing, and pavement markings.
  • Overhead diagram - Durant at Miller Rd. (PDF)

Current Phase

  • Design

Estimated project schedule

  • Design/Land acquisition completion: Early 2028
  • Procurement completion: Late 2028
  • Construction completion: Mid 2030

Project cost estimate

  • Total: $4,794,776
  • Planning: $4,957
  • Design and Land: $2,658,747
  • Construction: $2,131,072

Download a printable fact sheet for Durant at Miller Rd. intersection improvements (PDF)

Durant at Dover/Little Road intersection

Overview and objectives

  • To improve transportation, mobility, and access for vehicles and pedestrians including retrofitting to comply with the Americans with Disabilities Act (ADA), the four-way stop intersection will be converted to a roundabout with turning movement improvements and pedestrian enhancements. Sidewalks will be updated to improve pedestrian safety, specifically ADA ramps, curbing, and pavement markings.
  • Overhead diagram - Durant at Dover/Little Road (PDF)

Current phase

  • Design

Estimated project schedule

  • Design/Land acquisition: Mid 2026
  • Procurement completion: Early 2027
  • Construction completion: Late 2028

Project cost estimate:

  • Total: $4,461,219
  • Design and Land: $1,251,225
  • Construction: $3,209,994

Download a printable fact sheet for Durant at Dover/Little Road intersection (PDF)

Last Modified: 1/22/2026, 9:39:49 PM