Waters Avenue Force Main Replacement Project is a critical pipeline that serves as a principal transmission main for wastewater from west of Manhattan Avenue along Waters Avenue to Sheldon Road
Monday, July 13, 2026, 10:00 PM UTC
Town 'N Country Regional Public Library: 7606 Paula Dr. #120 Tampa, FL 33615
In-Person
Project highlights include:
- Replacing the aging 24-inch force main pipeline along Waters Avenue
- Installing Air Release Valves (ARVs) to prevent gas buildup and improve system performance
- Protecting the environment by reducing the risk of leaks or system failures
- Building the new pipeline to meet current Hillsborough County and Water Resource standards
Learn more about the project at the July 13, 2026, meeting.