Subdivision process fees information

Download Fee Schedule (PDF)

Subdivision process

Subdivision Preliminary Plat

Submittal

Resubmittal

2nd Resubmittal

Natural Resources Review

$509.88

n/a

$136.30

Stormwater Review

$369.07

n/a

$200

Site Engineering Review

$111.85

n/a

$100

Zoning Review

$529.39

n/a

n/a

Water/Wastewater Service Application

$373.83

n/a

n/a

Transportation- Site Access Review

$99.23

n/a

n/a

EPC Review

$460

n/a

$230

Fire Dept Review

$15

n/a

n/a

Grand Oaks Protection Review**

$479.27

n/a

n/a

Stormwater Master Plan Review (if applicable)

$1,500

n/a

$500

Street and Addresses Review (NEW)

$29.54

n/a

n/a

Subdivision Construction Plan

Submittal

Resubmittal

2nd & Additional Resubmittals

Natural Resources Review (1 to 50 lots)

$562.47

n/a

$192.64

Natural Resources Review (51-100 lots)

$558.33

n/a

$220.33

Natural Resources Review (Over 100 lots)

$666.20

n/a

$263.18

De minimis Natural Resources *

$250

n/a

$250

Stormwater Review (1 to 50 lots)

$1,726.11

n/a

$597.33

Stormwater Review (51-100 lots)

$1,747.47

n/a

$533.62

Stormwater Review (Over 100 lots)

$2,218.50

n/a

$626.66

Stormwater Inspections (1 to 50 lots)

$901.22

n/a

n/a

Stormwater Inspections (51-100 lots)

$1,221.23

n/a

n/a

Stormwater Inspections (Over 100 lots)

$4,070.77

n/a

n/a

Site Engineering Review (1 to 50 lots)

$1,333.82

n/a

$487.11

Site Engineering Review (51 to 100 lots)

$2,549.02

n/a

$935.32

Site Engineering Review (Over 100 lots)

$4,073.84

n/a

$1,357.75

Site Engineering Inspections (1 to 50 lots)

$814.66

n/a

n/a

Site Engineering Inspections (51 to 100 lots)

$1,221.23

n/a

n/a

Site Engineering Inspections (Over 100 lots)

$4,070.77

n/a

n/a

Utilities

$440.50

n/a

n/a

Zoning Review

$639.72

n/a

$297.25

EPC Review

$710

n/a

$355

Fire Dept Review

$15

n/a

n/a

Grand Oaks Protection Review **

$414.73

n/a

n/a

Street and Addresses (NEW)

$38.41

n/a

n/a

Utilities Reservation Capacity**

$301.56

n/a

n/a

Certificate of Capacity**

$35.79

n/a

n/a

Subdivision Construction Plan (Townhomes)

Submittal

Resubmittal

2nd & Additional Resubmittals

Natural Resources Review

$334.54/ Bldg

n/a

$193.06/ Bldg

Stormwater Review

$302.81/ Bldg

n/a

$597.94/ Bldg

Site Engineering Review

$ 231.15/ Bldg

n/a

$ 92.96/ Bldg

Utilities

$440.50

n/a

n/a

Zoning Review

$639.72

n/a

$297.25

EPC Review

$710

n/a

$355

Fire Dept Review

$15

n/a

n/a

Site Engineering Inspections (1 to 50 lots)

$814.66

n/a

n/a

Site Engineering Inspections (51 to 100 lots)

$1,221.23

n/a

n/a

Site Engineering Inspections (Over 100 lots)

$4,070.77

n/a

n/a

Stormwater Inspections (1 to 50 lots)

$901.22

n/a

n/a

Stormwater Inspections (51-100 lots)

$1,221.23

n/a

n/a

Stormwater Inspections (Over 100 lots)

$4,070.77

n/a

n/a

Utilities Reservation Capacity**

$301.56

n/a

n/a

Certificate of Capacity**

$35.79

n/a

n/a

Subdivision Final Plat (Full BOCC Acceptance)

Submittal

Resubmittal

2nd & Additional Resubmittals

Basic Fee

$426.13

n/a

$49.93

EPC Review

$260

n/a

$130

Site Engineering Review

$250

n/a

n/a

Stormwater Review

$250

n/a

n/a

Utilities

$149.34

n/a

n/a

Zoning Review

$639.72

n/a

$297.25

Street and Addresses (NEW)

$53.70

n/a

n/a

Survey (NEW)

$1,019.38

n/a

$306.82

Survey Mylar (NEW)

$106.96

n/a

n/a

Natural Resources Review 

$366.52

n/a

n/a

Subdivision Plat (BOCC Chairperson Acceptance) / Rural Minor Subdivision

Submittal

Resubmittal

2nd & Additional Resubmittals

Basic Fee

$135.80

n/a

n/a

EPC Review

$320

n/a

$130

Fire Dept Review

$15

n/a

n/a

Site Engineering Review

$250

n/a

n/a

Stormwater Review

$250

n/a

n/a

Utilities

$149.34

n/a

n/a

Zoning Review

$639.72

n/a

$297.25

Street and Addresses (NEW)

$53.70

n/a

n/a

Survey (NEW)

$1,019.38

n/a

$306.82

Survey Mylar (NEW)

$106.96

n/a

n/a

Natural Resources Review 

$366.52

n/a

n/a

Subdivision Plat (BOCC Chairperson Acceptance) /Urban Platted No Improvements

Submittal

Resubmittal

2nd & Additional Resubmittals

Basic Fee

$135.80

n/a

n/a

EPC Review

$260

n/a

$130

Fire Dept Review

$15

n/a

n/a

Site Engineering Review

$250

n/a

n/a

Stormwater Review

$250

n/a

n/a

Utilities

$149.34

n/a

n/a

Zoning Review

$639.72

n/a

$297.25

Street and Addresses (NEW)

$53.70

n/a

n/a

Survey (NEW)

$1,019.38

n/a

$306.82

Survey Mylar (NEW)

$106.96

n/a

n/a

Natural Resources Review 

$366.52

n/a

n/a

Certified Parcel Review

Submittal

Resubmittal

2nd & Additional Resubmittals

Basic Fee (per lot)

$299.32

n/a

n/a

EPC Review

$320

n/a

n/a

As -Builts

Submittal

Resubmittal

2nd & Additional Resubmittals

Basic Fee (New)

$388.75

n/a

n/a

EPC Verification

$400

n/a

n/a

BOCC Acceptance of Improvements

$135

n/a

n/a

Land Use Hearing Officer Review

Submittal

Resubmittal

2nd & Additional Resubmittals

Basic Fee

$600

n/a

n/a

EPC Review

$260

n/a

n/a

Additional review fee for projects on IPD Districts

$130

n/a

n/a

** Fee to be paid at the end of review only if determined to be applicable.

Note: For all projects, additional agencies may require review without a fee.


See Site Development Process Fees