#83253000
Quick Facts
- Location: City Of Tampa
- Project Type: Parks and Recreation
- Phase: Completed
Schedule
- Planning complete: Late 2014
- Design complete: Early 2016
- Construction begins: Early 2017
- Construction complete: Late 2017
Budget Breakdown
- Total: $908,805
- Construction: $908,805
Overview
- Provide funding for amenities such as shade structures, bike racks, signs, benches, trash receptacles, etc. to the new trail. The design and construction will be done by the City of Tampa.
Objectives
- Support the new 5.5 miles of trail constructed by FDOT at Courtney Campbell Causeway from Bayport Dr. to the Hillsborough County Line.
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.
Current as of 5/30/2025