#69695000

Quick Facts

  • Location: Lithia
  • Project Type: Intersections
  • Phase: Planning

Schedule

  • Planning complete: Early 2026
  • Design complete: TBD
  • Construction begins: TBD
  • Construction complete: TBD

Budget Breakdown

  • Total: $10,900,000
    • Planning: $353,146.58
    • Design and Land: $3,325,799
    • Construction: $7,221,054

Overview

  • Provide left turn lanes on all approaches and a right turn lane in the north direction. Update signals, signage, and pavement markings to include pedestrian considerations. Upgrade drainage and add pond to accommodate additional pavement for turn lanes, bicycle lanes, traffic separators, sidewalks, and curb and gutter.
  • Upgrade drainage and add pond to accommodate additional pavement for turn lanes, bicycle lanes, traffic separators, sidewalks, and curb and gutter.

Objectives

  • Safety Study performed by Benesch, at the request of the County, recommending safety and mobility improvements by adding turn lanes and pedestrian and bicycle facilities at the intersection of S County Road 39 and Lithia Pinecrest Road.

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 1/23/2026