#69692000
Quick Facts
- Location: Gibsonton
- Project Type: Roadway Corridor Improvements
- Phase: Design
Schedule
- Planning complete: N/A
- Design complete: Mid 2026
- Construction begins: Late 2026
- Construction complete: Mid 2028
Budget Breakdown
- Total: $26,464,892
- Design and Land: $788.13
- Construction: $26,464,103.87
Overview
- The project improves 0.75 miles of Big Bend Road by widening it from 4 to 6 lanes with new sidewalks, drainage, curb and gutter, and a median. It adds a traffic signal at Old Big Bend Road/Kings Lake Drive and converts Covington Garden Drive to a 3‑leg intersection. Kings Lake Drive will be resurfaced, a southbound left‑turn lane added, and an 8–12 ft trail built along Waterset Boulevard to the Scenic Drive Trailhead.
Objectives
- The project aims to improve capacity, reduce traffic congestion, and enhance safety and provide operational improvements along the corridor.
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.
Current as of 7/10/2026