#69685000

Quick Facts

  • Location: Lithia
  • Project Type: Pedestrian and Bike Facilities
  • Phase: Completed

Schedule

  • Planning complete: Mid 2023
  • Design complete: TBD
  • Construction begins: TBD
  • Construction complete: TBD

Budget Breakdown

  • Total: $20,100,000
    • Planning: $86,469.74
    • Design and Land: $1,400,000
    • Construction: $18,613,530.26

Overview

  • The alternatives for the 5.5 mile alignment of the trail connecting Balm Boyette Scrub Preserve to Alafia River State Park will be evaluated for feasibility, cost, and ability to meet County objectives.
  • Project development will include identifying and analyzing trail user needs, alignment constraints, Right-Of-Way needs, and details of the project

Objectives

  • Improve pedestrian aCess.
  • Increase safety of pedestrians and bicyclists.
  • multipoint
  • multipoint

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 5/30/2025