#69679130

Quick Facts

  • Location: Lithia
  • Project Type: Intersections
  • Phase: Design

Schedule

  • Planning complete: N/A
  • Design complete: Early 2026
  • Construction begins: Late 2026
  • Construction complete: Mid 2027

Budget Breakdown

  • Total: $450,000
    • Design and Land: $100,000
    • Construction: $350,000

Overview

  • This interim project focuses on enhancing traffic operations and safety at the intersection of Lithia Pinecrest Road and County Road 39. The scope includes the addition of a northbound left-turn lane and extend the existing southbound right-turn lane to improve vehicle flow and reduce delays. These enhancements aim to alleviate congestion and minimize conflict points at the intersection, providing immediate operational benefits while the long-term Tier 3 improvements are still under design.

Objectives

  • This interim project focuses on enhancing traffic operations and safety at the intersection of Lithia Pinecrest Road and County Road 39. The scope includes the addition of a northbound left-turn lane and extend the existing southbound right-turn lane to improve vehicle flow and reduce delays. These enhancements aim to alleviate congestion and minimize conflict points at the intersection, providing immediate operational benefits while the long-term Tier 3 improvements are still under design.

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 1/23/2026