#69679040

Quick Facts

  • Location: Summerfield
  • Project Type: Intersections
  • Phase: Completed

Schedule

  • Planning complete: N/A
  • Design complete: Late 2020
  • Construction begins: Late 2020
  • Construction complete: Late 2021

Budget Breakdown

  • Total: $1,721,403.85
    • Design and Land: $157,629.53
    • Construction: $1,563,774.32

Overview

  • Addition of a westbound emergency lane for the exclusive use of the Fire Rescue, a two-foot-wide traffic separator, a westbound left and through lane, a westbound right turn lane at the intersection of Rhodine Road and US Highway 301.
  • Also includes the offsite components related to the design for a westbound left turn lane and an eastbound right turn lane along Rhodine Rd at the main driveway into the Consolidated & Hardened Maintenance Facility (CHMF) - South (CIP No. C-77832000).

Objectives

  • Accommodate hardened maintenance and fire station facilities to be located east of the intersection.
  • Improve transportation mobility and safety for vehicles and pedestrians.
  • multipoint
  • multipoint

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 4/11/2025