#69679039
Quick Facts
- Location: Summerfield
- Project Type: Intersections
- Phase: Completed
Schedule
- Planning complete: N/A
- Design complete: Early 2020
- Construction begins: Late 2021
- Construction complete: Mid 2022
Budget Breakdown
- Total: $746,961.06,005
- Design and Land: $72,541.06
- Construction: $674,420.00,005
Overview
- The intent of this project is to supplement the roadway improvements being implemented along both Balm Riverview Road and Rhodine Road as part of CIP 69645106.
- The existing flashing beacon will be replaced with a signal.
Objectives
- Improve transportation mobility and safety for vehicles and pedestrians.
- Upgrade existing transportation facilities, including retrofitting for Americans with Disability Act, or ADA compliance, to provide services that improve access for all users.
- multipoint
- multipoint
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.
Current as of 5/30/2025