#69679027

Quick Facts

  • Location: Summerfield
  • Project Type: Intersections
  • Phase: Completed

Schedule

  • Planning complete: N/A
  • Design complete: N/A
  • Construction begins: Mid 2021
  • Construction complete: Mid 2023

Budget Breakdown

  • Total: $1,275,193.66
    • Design and Land: $172,611.97

Overview

  • Improvements including but not limited to: converting unsignalized intersections to signalized with turn lane improvements and pedestrian enhancements; alternative to modify the median openings.
  • Sidewalks will be added or replaced to improve pedestrian connectivity through the corridor specifically, ADA ramps, curbing and pavement markings.

Objectives

  • Countywide operation and safety improvements to the roadway system through intersection and access enhancements in high crash and high congestion locations.
  • Upgrade existing transportation facilities, including retrofitting for Americans with Disability Act, or ADA compliance, to provide services that improve access for all users.
  • multipoint
  • multipoint

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 7/11/2025