#69679013
Quick Facts
- Location: Usf
- Project Type: Intersections
- Phase: Construction
Schedule
- Planning complete: N/A
- Design complete: Mid 2023
- Construction begins: Late 2024
- Construction complete: Early 2026
Budget Breakdown
- Total: $10,473,883.81
- Design and Land: $1,132,978.97
- Construction: $9,340,904.84
Overview
- This project is part of the Intersection Operation and Safety Enhancement Program. Intersection improvements at 50th Street and Holly Drive will include a signal and pedestrian features.
- Additional intersection improvements will be made at 50th Street and Fletcher Avenue to include an additional northbound left turn lane and eastbound right turn lane.
Objectives
- Improve transportation mobility and safety for vehicles and pedestrians.
- Upgrade existing transportation facilities, including retrofitting for Americans with Disability Act, or ADA compliance, to provide services that improve access for all users.
- multipoint
- multipoint
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.
Current as of 6/13/2025