#69679009

Quick Facts

  • Location: Town-N-Country
  • Project Type: Intersections
  • Phase: Construction

Schedule

  • Planning complete: N/A
  • Design complete: Mid 2023
  • Construction begins: Late 2025
  • Construction complete: Early 2026

Budget Breakdown

  • Total: $2,361,876.48
    • Design and Land: $177,725.98
    • Construction: $2,184,150.5

Overview

  • Functional improvements to the intersection of George Road at Memorial Highway through turn lane additions including but not limited to a southbound right turn lane, and an extension of the westbound left turn lane.
  • Sidewalks will be added or replaced to improve pedestrian connectivity through the corridor. ADA ramps, curbing and pavement markings will be brought to code.

Objectives

  • Improve transportation mobility and safety for vehicles and pedestrians.
  • Upgrade existing transportation facilities, including retrofitting for Americans with Disability Act, or ADA compliance, to provide services that improve access for all users.
  • multipoint
  • multipoint

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 3/27/2026