#69679008

Quick Facts

  • Location: Lutz
  • Project Type: Intersections
  • Phase: Design

Schedule

  • Planning complete: Early 2018
  • Design complete: Early 2027
  • Construction begins: Late 2028
  • Construction complete: Mid 2030

Budget Breakdown

  • Total: $3,038,355.7
    • Design and Land: $1,038,103.7
    • Construction: $2,000,252

Overview

    Intersection improvements including, but not limited to, addition of westbound to southbound dual left turn lanes on Sunset Lane and signal rebuild. Sidewalks will be added or replaced to improve pedestrian connectivity through the corridor specifically, ADA ramps, curbing and pavement markings.

Objectives

    Improve transportation mobility and safety for vehicles and pedestrians. Upgrade existing transportation facilities, including retrofitting for Americans with Disability Act, or ADA compliance, to provide services that improve access for all users.

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.