Quick Facts

  • Location: Riverview
  • Project Type: Intersections
  • Phase: Design

Schedule

  • Planning complete: Mid 2019
  • Design complete: Early 2029
  • Construction begins: Late 2029
  • Construction complete: Mid 2031

Budget Breakdown

  • Total: $14,852,806.39
    • Design and Land: $2,852,643.89
    • Construction: $12,000,162.5

Overview

    This project includes a series of intersection improvements. The work will add a second through lane on Balm Riverview Road, new right‑turn lanes on the northbound, westbound, and eastbound approaches, and several pedestrian focused enhancements. Sidewalks will be added or replaced to strengthen pedestrian connectivity throughout the corridor, along with updated ramps, curbing, and pavement markings.

Objectives

    The project will improve mobility and safety for both vehicles and pedestrians by upgrading the existing transportation facilities. This includes bringing the corridor into compliance with the Americans with Disabilities Act standards.

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.