#69679005

Quick Facts

  • Location: Palm River
  • Project Type: Intersections
  • Phase: Design

Schedule

  • Planning complete: N/A
  • Design complete: Late 2026
  • Construction begins: Late 2027
  • Construction complete: Late 2028

Budget Breakdown

  • Total: $8,825,689.29
    • Planning: $32,324.67
    • Design and Land: $4,793,364.62
    • Construction: $4,000,000

Overview

  • Intersection improvements including, but not limited to, evaluation the need for additional capacity, extend existing turn lanes and evaluate the need to rebuild the existing signal. Study alternatives to convert to roundabout.
  • Add keyhole lanes, and provide pedestrian crosswalk and pedestrian signals on all four legs of the intersection.

Objectives

  • Improve transportation mobility and safety for vehicles and pedestrians.
  • Upgrade existing transportation facilities, including retrofitting for Americans with Disability Act, or ADA compliance, to provide services that improve access for all users.
  • multipoint
  • multipoint

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 6/27/2025