#69679004

Quick Facts

  • Location: Seffner
  • Project Type: Intersections
  • Phase: Design

Schedule

  • Planning complete: Late 2020
  • Design complete: Late 2028
  • Construction begins: Late 2029
  • Construction complete: Mid 2031

Budget Breakdown

  • Total: $8,725,863.18
    • Planning: $70,782.66
    • Design and Land: $4,655,080.52
    • Construction: $4,000,000

Overview

    The project provides a new signal at the intersection, designated turn lanes, enhanced sidewalk, new sidewalk, including stormwater management system.

Objectives

    The purpose of this project is to increase vehicle capacity and improve safety and mobility for pedestrians and bicyclists. The upgraded intersection will also include features compliant with the Americans with Disabilities Act to ensure accessible and reliable travel for all users.

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.