#69679002
Quick Facts
- Location: Town-N-Country
- Project Type: Intersections
- Phase: Procurement
Schedule
- Planning complete: Late 2020
- Design complete: Early 2026
- Construction begins: Late 2028
- Construction complete: Late 2031
Budget Breakdown
- Total: $1,638,400.16
- Design and Land: $638,400.16
- Construction: $1,000,000
Overview
Improvements include installing new sidewalk,Americans with Disability (ADA) ‑compliant curb ramps, pavement markings, and separating pedestrian push buttons at each crossing.
Objectives
Improve transportation mobility and safety for vehicles and pedestrians. Upgrade existing transportation facilities, including retrofitting for Americans with Disability Act, or ADA compliance, to provide services that improve access for all users.
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.