#69666000

Quick Facts

  • Location: Palm River
  • Project Type: Roadway Corridor Improvements
  • Phase: Design

Schedule

  • Planning complete: N/A
  • Design complete: Late 2025
  • Construction begins: TBD
  • Construction complete: TBD

Budget Breakdown

  • Total: $1,771,554
    • Design and Land: $1,771,554

Overview

    Enhancement of S 78th Street, a 2-lane undivided road, from Progress Boulevard to Causeway Boulevard including turn lane improvements.

Objectives

    Reduce traffic congestion and improve safety for drivers, pedestrians and bicyclists.

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.