#69657000

Quick Facts

  • Location: Gibsonton
  • Project Type: Intersections
  • Phase: Completed

Schedule

  • Planning complete: Early 2020
  • Design complete: Mid 2021
  • Construction begins: Mid 2021
  • Construction complete: Early 2025

Budget Breakdown

  • Total: $82,000,000
    • Design and Land: $280,530.35
    • Construction: $81,719,469.65

Overview

    Big Bend Rd from Covington Gardens Dr to Simmons Loop will be widened from a 4-lane to a 6-lane divided road with enhanced bike, pedestrian and bus facilities, with reconfiguration and improvements to the ramps. Improvements to be designed and constructed by Florida Department of Transportation (FDOT).

Objectives

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.