#69657000
Quick Facts
- Location: Gibsonton
- Project Type: Intersections
- Phase: Completed
Schedule
- Planning complete: Early 2020
- Design complete: Mid 2021
- Construction begins: Mid 2021
- Construction complete: Early 2025
Budget Breakdown
- Total: $61,132,799
- Design and Land: $270,530.35
- Construction: $60,862,268.65
Overview
- Big Bend Rd from Covington Gardens Dr to Simmons Loop will be widened from a 4-lane to a 6-lane divided road with enhanced bike, pedestrian and bus facilities, with reconfiguration and improvements to the ramps. Improvements to be designed and constructed by Florida Department of Transportation (FDOT).
- Other improvements include reconstruction of the bridges on Old Big Bend Rd and Big Bend Rd, signal improvements at Covington Gardens Dr and Simmons Loop, and increasing stormwater drainage.
Objectives
- Better accommodate growth and traffic volume.
- multipoint
- multipoint
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.