#69657000
Quick Facts
- Location: Gibsonton
- Project Type: Intersections
- Phase: Completed
Schedule
- Planning complete: Early 2020
- Design complete: Mid 2021
- Construction begins: Mid 2021
- Construction complete: Early 2025
Budget Breakdown
- Total: $82,000,000
- Design and Land: $280,530.35
- Construction: $81,719,469.65
Overview
Big Bend Rd from Covington Gardens Dr to Simmons Loop will be widened from a 4-lane to a 6-lane divided road with enhanced bike, pedestrian and bus facilities, with reconfiguration and improvements to the ramps. Improvements to be designed and constructed by Florida Department of Transportation (FDOT).
Objectives
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.