#69657000

Quick Facts

  • Location: Gibsonton
  • Project Type: Intersections
  • Phase: Completed

Schedule

  • Planning complete: Early 2020
  • Design complete: Mid 2021
  • Construction begins: Mid 2021
  • Construction complete: Early 2025

Budget Breakdown

  • Total: $61,132,799
    • Design and Land: $270,530.35
    • Construction: $60,862,268.65

Overview

  • Big Bend Rd from Covington Gardens Dr to Simmons Loop will be widened from a 4-lane to a 6-lane divided road with enhanced bike, pedestrian and bus facilities, with reconfiguration and improvements to the ramps. Improvements to be designed and constructed by Florida Department of Transportation (FDOT).
  • Other improvements include reconstruction of the bridges on Old Big Bend Rd and Big Bend Rd, signal improvements at Covington Gardens Dr and Simmons Loop, and increasing stormwater drainage.

Objectives

  • Better accommodate growth and traffic volume.
  • multipoint
  • multipoint

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 8/25/2026