#69647000

Quick Facts

  • Location: Multiple
  • Project Type: Roadway Corridor Improvements
  • Phase: Construction

Schedule

  • Planning complete: Mid 2021
  • Design complete: Mid 2024
  • Construction begins: Early 2025
  • Construction complete: Early 2027

Budget Breakdown

  • Total: $44,704,145.33
    • Planning: $1,860,209.17
    • Design and Land: $5,693,936.16
    • Construction: $37,150,000

Overview

  • Corridor improvement for Big Bend Rd from US 41 to Covington Gardens Dr and from Simmons Loop to US 301 from a 4-lane divided road to a 6-lane divided road with enhanced bike, pedestrian and bus facilities.
  • Enhance pedestrian safety features, including wide sidewalks and enhanced crosswalks and signals. Stormwater drainage will also be improved.

Objectives

  • Better accommodate growth and traffic volume.
  • Increase the overall mobility along Big Bend Road, while maximizing safety along the corridor.
  • multipoint
  • multipoint

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 6/27/2025