Schedule

  • Planning complete: Mid 2021
  • Design complete: Mid 2024
  • Construction begins: Early 2025
  • Construction complete: Mid 2027

Budget Breakdown

  • Total: $44,825,655.81
    • Planning: $1,443,736.75
    • Design and Land: $6,207,406.26
    • Construction: $37,174,512.8

Overview

  • The corridor improvement project for Big Bend Road will widen the roadway from a 4 lane divided road to a 6 lane divided road between US 41 and Covington Gardens Drive, and from Simmons Loop to US 301. The project will also add enhanced bicycle, pedestrian, and bus facilities along the corridor. Improvements include wider sidewalks, upgraded crosswalks and signals, and improvements to stormwater drainage.

Objectives

  • This project will improve capacity, enhance safety, and provide operational improvements along the Big Bend Road corridor. These upgrades aim to support current and future travel needs while creating a more efficient and reliable transportation route for all users.
  • multipoint
  • multipoint

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service