#69646000

Quick Facts

  • Location: Lutz
  • Project Type: Roadway Corridor Improvements
  • Phase: Design

Schedule

  • Planning complete: Mid 2020
  • Design complete: Mid 2025
  • Construction begins: TBD
  • Construction complete: TBD

Budget Breakdown

  • Total: $93,023,662
    • Planning: $2,772,532.38
    • Design and Land: $37,251,129.62
    • Construction: $53,000,000

Overview

  • Corridor improvements for Van Dyke Rd, from Whirley Rd to Suncoast Pkwy (approximately 2 miles) from a 2-lane undivided road, to a 4-lane divided facility. Includes enhanced pedestrian, bicycle facilities and improvements to the associated stormwater drainage.
  • Additional items are: intersection improvements, enhanced pedestrian safety features such as sidewalks, enhanced crosswalks and signals. A shared-use trail connection from the Upper Tampa Bay Trail to the Northdale Lake Park Trail will also be provided.

Objectives

  • Reduce traffic congestion and improve safety for drivers, pedestrians and bicyclists.
  • Increase the overall mobility along Van Dyke Rd while maximizing safety along the corridor.
  • multipoint
  • multipoint

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 6/13/2025