#69646000
Quick Facts
- Location: Lutz
- Project Type: Roadway Corridor Improvements
- Phase: Design
Schedule
- Planning complete: Mid 2020
- Design complete: Early 2026
- Construction begins: TBD
- Construction complete: TBD
Budget Breakdown
- Total: $135,582,423.08
- Planning: $2,901,222.51
- Design and Land: $47,868,626.84
- Construction: $84,812,573.73
Overview
- Corridor improvements for Van Dyke Rd, from Whirley Rd to Suncoast Pkwy (approximately 2 miles) from a 2-lane undivided road, to a 4-lane divided facility. Includes enhanced pedestrian, bicycle facilities and improvements to the associated stormwater drainage.
- Additional items are: intersection improvements, enhanced pedestrian safety features such as sidewalks, enhanced crosswalks and signals. A shared-use trail connection from the Upper Tampa Bay Trail to the Northdale Lake Park Trail will also be provided.
Objectives
- Reduce traffic congestion and improve safety for drivers, pedestrians and bicyclists.
- Increase the overall mobility along Van Dyke Rd while maximizing safety along the corridor.
- multipoint
- multipoint
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.
Current as of 3/27/2026