Schedule

  • Planning complete: N/A
  • Design complete: N/A
  • Construction begins: Mid 2026
  • Construction complete: Early 2027

Budget Breakdown

  • Total: $196,675
    • Design and Land: $15,000
    • Construction: $181,675

Overview

    Construction of pedestrian improvements at Covington Garden Dr from South of Covington Stone Avenue to North of Bristol Park Drive. Improvements include pedestrian signage, pavement markings, and installation of Rectangular Rapid Flashing Beacons.

Objectives

    This project will increase pedestrian visibility and safety at Covington Garden Dr, which is a student walking route for Dolby Elementary School. The improvements were recommended based on data collection activities, collision analysis, qualitative assessment, field observations, and engineering judgment

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.