#69631104
Quick Facts
- Location: City Of Tampa
- Project Type: Resurfacing
- Phase: Construction
Schedule
- Planning complete: Late 2019
- Design complete: Late 2022
- Construction begins: Late 2025
- Construction complete: Mid 2026
Budget Breakdown
- Total: $2,666,956.07
- Design and Land: $189,063.6
- Construction: $2,477,892.47
Overview
- This project is part of the Roadway Pavement Preservation Program, which includes condition inspection, routine repairs, preventative maintenance treatments and road repaving projects.
- Resurfacing along N West Shore Blvd. from W. Kennedy Blvd. to W. Spruce St / W. Boy Scout Blvd.
Objectives
- Maintain the County's roads in a safe and serviceable condition for the lowest cost to the community.
- Improve travel reliability and efficiency of the existing roadway to support a multimodal system.
- multipoint
- multipoint
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.
Current as of 2/13/2026