Mosquito OperationsRead the latest updates and detailed information

#69631104

Quick Facts

  • Location: City Of Tampa
  • Project Type: Resurfacing
  • Phase: Closeout

Schedule

  • Planning complete: Late 2019
  • Design complete: Late 2022
  • Construction begins: Late 2025
  • Construction complete: Mid 2026

Budget Breakdown

  • Total: $2,666,956.07
    • Design and Land: $189,063.6
    • Construction: $2,477,892.47

Overview

    This project is part of the Roadway Pavement Preservation Program, which includes condition inspection, routine repairs, preventative maintenance treatments and road repaving projects. Resurfacing along N West Shore Blvd. from W. Kennedy Blvd. to W. Spruce St / W. Boy Scout Blvd.

Objectives

    Maintain the County's roads in a safe and serviceable condition for the lowest cost to the community. Improve travel reliability and efficiency of the existing roadway to support a multimodal system.

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.