#69200311
Quick Facts
- Location: Citrus Park
- Project Type: Bridge
- Phase: Construction
Schedule
- Planning complete: N/A
- Design complete: Early 2024
- Construction begins: Late 2024
- Construction complete: Mid 2025
Budget Breakdown
- Total: $2,272,785.82
- Design and Land: $280,288.45
- Construction: $1,992,497.37
Overview
- This project is a part of the Community Investment Tax (CIT) Funded Bridge Improvements Program. The project includes removal of the existing bridge, design, permitting and construction of a new bridge.
- The new bridge will have modern safety features, such as concrete traffic barriers, and sidewalks and road shoulders or bike lanes will be added.
Objectives
- Maintain serviceability, reduce deterioration, and preserve structural integrity.
- Avoid expensive replacement costs in the future.
- multipoint
- multipoint
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.
Current as of 5/9/2025