#69200106

Quick Facts

  • Location: Gibsonton
  • Project Type: Bridge
  • Phase: Procurement

Schedule

  • Planning complete: Mid 2019
  • Design complete: Late 2023
  • Construction begins: Mid 2025
  • Construction complete: Late 2025

Budget Breakdown

  • Total: $2,412,119.39
    • Design and Land: $411,582.89
    • Construction: $2,000,536.5

Overview

  • This project is a part of the Community Investment Tax (CIT) Funded Bridge Improvements Program. The project includes removal of the existing bridge, design, permitting and construction of a new bridge.
  • The new bridge will have modern safety features, such as concrete traffic barriers, and sidewalks and road shoulders or bike lanes will be added.

Objectives

  • Maintain serviceability, reduce deterioration, and preserve structural integrity.
  • Avoid expensive replacement costs in the future.
  • multipoint
  • multipoint

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 5/30/2025