Quick Facts
- Location: City Of Temple Terrace
- Project Type: Roadway Operations and Safety
- Phase: Completed
Schedule
- Planning complete: Mid 2013
- Design complete: Late 2015
- Construction begins: Early 2018
- Construction complete: Late 2019
Budget Breakdown
- Total: $1,154,256
- Construction: $1,154,256
Overview
- This project is part of the Dangerous Intersection/Pedestrian Safety Program.
- Enhance pedestrian and bicycle safety features along 56th St. from Fowler Ave. to Fletcher Ave.
Objectives
- Improve pedestrian and bicyclist safety.
- Improve pedestrian and bicyclist mobility.
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.
Current as of 4/11/2025