Schedule

  • Planning complete: Mid 2013
  • Design complete: Late 2015
  • Construction begins: Early 2018
  • Construction complete: Late 2019

Budget Breakdown

  • Total: $1,154,256
    • Construction: $1,154,256

Overview

  • This project is part of the Dangerous Intersection/Pedestrian Safety Program.
  • Enhance pedestrian and bicycle safety features along 56th St. from Fowler Ave. to Fletcher Ave.

Objectives

  • Improve pedestrian and bicyclist safety.
  • Improve pedestrian and bicyclist mobility.