#46185000

Quick Facts

  • Location: Palm River
  • Project Type: Stormwater and Water Quality Improvements
  • Phase: Construction

Schedule

  • Planning complete: Late 2022
  • Design complete: Mid 2024
  • Construction begins: Mid 2025
  • Construction complete: Mid 2025

Budget Breakdown

  • Total: $16,129,545
    • Design and Land: $1,316,416.92
    • Construction: $14,813,128.08

Overview

  • Project will evaluate and develop regional flood protection/water quality improvement.
  • Project may reduce significantly flooding within the Progress Village Neighborhood

Objectives

  • The Project will provide flood protection and Water Quality benefit.
  • multipoint
  • multipoint

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 4/11/2025