#46142873

Quick Facts

  • Location: Brandon
  • Project Type: Culvert Repair and Replacement
  • Phase: Construction

Schedule

  • Planning complete: TBD
  • Design complete: TBD
  • Construction begins: TBD
  • Construction complete: TBD

Budget Breakdown

  • Total: $157,535.25
    • Construction: $157,535.25

Overview

  • This project will address Maintstar WO ST 42361. Remove and replace four pipes along with four catch basins. Add two mitered end sections. Pavement Restoration per UAG Appendix K.
  • N/a

Objectives

  • This project will address Maintstar WO ST 42361 as an emergency culvert replacement.

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 4/11/2025