#46142857

Quick Facts

  • Location: Thonotosassa
  • Project Type: Culvert Repair and Replacement
  • Phase: Completed

Schedule

  • Planning complete: N/A
  • Design complete: N/A
  • Construction begins: Early 2024
  • Construction complete: Mid 2024

Budget Breakdown

  • Total: $114,289.94
    • Construction: $114,289.94

Overview

  • This project is part of the Neighborhood Drainage Improvements Program.
  • This project will replace two existing 42"x72" CMP culverts in state of disrepair with a hydraulically equivalent box culvert.

Objectives

  • Prevent damage from potential infrastructure failure.

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.