#46134029

Quick Facts

  • Location: East Lake
  • Project Type: Stormwater and Water Quality Improvements
  • Phase: Completed

Schedule

  • Planning complete: Mid 2015
  • Design complete: Mid 2018
  • Construction begins: Early 2019
  • Construction complete: Early 2020

Budget Breakdown

  • Total: $1,809,755
    • Planning: $19,644
    • Design and Land: $153,551
    • Construction: $1,636,560

Overview

  • Project includes a PD&E study and survey to investigate solutions to alleviate road flooding along Temple Terrace Hwy (TTH) near 8300 TTH between Meadowood Blvd and Hamilton Hill Ln.
  • Construction of approximately 1600 Linear Feet 16 inch Force Main from existing retention pond on Temple Terrace Hwy. to 78th St., and along 78th Street to Hillsborough River north of Temple Terrace Hwy.

Objectives

  • This project is part of the Water Quality Improvement and Environmental Program.
  • To meet State requirements for Total Maximum Daily Loads (TMDL) related to impaired waters.

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 3/27/2026