#41142002
Quick Facts
- Location: Lithia
- Project Type: Stormwater and Water Quality Improvements
- Phase: Completed
Schedule
- Planning complete: Early 2020
- Design complete: Early 2020
- Construction begins: N/A
- Construction complete: N/A
Budget Breakdown
- Total: $1,000,000
- Design and Land: $1,000,000
Overview
- The study done on this project was completed in 2002 and updated 2006. Reports contain information on data collection, model calibration/verification, and existing conditions for water quantity, water quality and natural systems within the watershed.
- Recommendations in the reports from the study supported the CIP, but at the time of improvements the SWFWMD’s guideline and specification (G&S) was not available and land has changed in many areas of the watershed.
Objectives
- Improve water quality of the community by improving the County’s stormwater infrastructure.
- Update the model following the G&S, pick land use changes, develop HC-SWMM5 GWIS and identify flooding.
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.
Current as of 4/11/2025