#41142002

Quick Facts

  • Location: Lithia
  • Project Type: Stormwater and Water Quality Improvements
  • Phase: Completed

Schedule

  • Planning complete: Early 2020
  • Design complete: Early 2020
  • Construction begins: N/A
  • Construction complete: N/A

Budget Breakdown

  • Total: $1,000,000
    • Design and Land: $1,000,000

Overview

  • The study done on this project was completed in 2002 and updated 2006. Reports contain information on data collection, model calibration/verification, and existing conditions for water quantity, water quality and natural systems within the watershed.
  • Recommendations in the reports from the study supported the CIP, but at the time of improvements the SWFWMD’s guideline and specification (G&S) was not available and land has changed in many areas of the watershed.

Objectives

  • Improve water quality of the community by improving the County’s stormwater infrastructure.
  • Update the model following the G&S, pick land use changes, develop HC-SWMM5 GWIS and identify flooding.

Questions?

For more information about this project please contact (813) 635-5400 or visit At Your Service

Leave a Comment

Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.

Current as of 4/11/2025