#10323000
Quick Facts
- Location: Town-N-Country
- Project Type: Waste Water
- Phase: Design
Schedule
- Planning complete: Late 2022
- Design complete: Mid 2026
- Construction begins: Late 2026
- Construction complete: Early 2029
Budget Breakdown
- Total: $50,000,000
Overview
- Hillsborough County will be replacing approximately 22,000 feet of the existing 24-inch force main along Waters Avenue. The new pipeline will be constructed within the existing road right-of-way, extending from west of N. Manhattan Avenue to Sheldon Road
Objectives
- Maintain Reliable Wastewater Service Safeguard Environmental Quality Replace Aging Wastewater Infrastructure Long Term Cost Savings
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.
Current as of 7/17/2026