#69679048
Quick Facts
- Location: Carrollwood
- Project Type: Intersections
- Phase: Closeout
Schedule
- Planning complete: N/A
- Design complete: N/A
- Construction begins: Late 2023
- Construction complete: Early 2025
Budget Breakdown
- Total: $4,863,842.27
- Planning: $32,313.57
- Design and Land: $692,702.64
- Construction: $4,138,826.06
Overview
- Intersection improvements including but not limited to dual eastbound lefts, conversion of the northbound right turn lane to a shared auxiliary through and right lane for two effective northbound thru lanes.
- Project is currently in construction. This CIP is open for the consultant to charge post design.
Objectives
- Improve transportation mobility and safety for vehicles and pedestrians.
- Upgrade existing transportation facilities, including retrofitting for Americans with Disability Act, or ADA compliance, to provide services that improve access for all users.
- multipoint
- multipoint
Questions?
For more information about this project please contact (813) 635-5400 or visit At Your Service
Note: The cost and schedule data shown here are the County's current best estimates and are subject to frequent change. Changes (if any) are updated weekly.
Current as of 5/9/2025